01Structural method
The structural (shell) phase runs on a documented 21-stage programme: site hoarding, excavation and foundation setting-out, then the reinforced concrete frame stage by stage, through to a building complete in its structural state. The sequence is the same on every project, which is what makes a construction programme estimable rather than optimistic.
See the 21 stages02Design and build
This project was delivered design-build: architectural, structural and MEP design plus execution under one contract and one accountable party. It removes the usual gap between designer and contractor, so clashes between systems are resolved on the drawings rather than in poured concrete.
Architectural works03Interior and external finishing
The finishing phase begins with preparatory works and ends with the project handed over ready for use. It covers full interior design implementation, interior and exterior finishing, façade works, joinery and façade lighting, with material quality control and adherence to the approved design under continuous supervision that harmonises every trade on site.
Finishing works04Quality control and safety
Each of the 21 structural stages carries its own verification, and supervision re-inspects after every strike of formwork. BRU CO. is certified to ISO standards for quality, safety and environmental management, and site safety requirements apply for the full duration of the works.
Quality and safety